The majority of the sulphide concentrating equipment is on site and a significant proportion is installed. Construction is progressing on time and on budget with first sulphide production scheduled for Q3 2017. There will be a increase in installed primary milling capacity once the sulphide plant is commissioned, from 20,000 to 40,000 t/month.